Pipeline & Civil Infrastructure

12’ CARBON STEEL LINES

•$15,000,000 

• Project Scope, design two 12” carbon steel lines to provide flexibility between two local facilities and main distribution pipe line 

• 160 caissons throughout an existing storage tank facility 

• Estimated and tracked man hours and costs to complete the project 

• Developed an accurate projected schedule including coordinating tie ins with multiple operating unit outages

• Identifying constructability analysis 

Featured Performance

PAST PERFORMANCE LEDGER

Mainline Transmission & Gathering:

  • Installation of 400+ LF of 6” Schedule 40 carbon steel systems including knock-out drum integration.

  • Turnkey installation of high-pressure gathering lines utilizing Zap-lok and Flexsteel technology for rapid deployment.

  • Execution of 100 LF of 2” Schedule 80 socket-weld condensate lines for facility tie-ins.

Civil & Right-of-Way (ROW) Management:

  • Large-Scale Utility Clearing: Comprehensive brush clearing and vegetation management for multi-mile transmission corridors.

  • Advanced Earthwork: Precision ditching and trenching for multi-line bundles in diverse soil conditions.

  • Road & River Crossings: Managing horizontal boring and "Live Line" crossing protocols with 100% safety compliance.

Testing & Integrity:

  • Hydrostatic Testing: High-pressure validation of new and existing mainline assets to ensure jurisdictional compliance.

  • Anomaly Excavation: Strategic "Integrity Digs" and structural reinforcements for buried pipeline assets.

Specialty Project

CHEMICAL PLANT

• $50,000
• Replace Existing Tank Bottom with New Material
• Open Top Tank inside a manufacturing facility
• Cut off and reinstall existing anchor chairs
• Replacement was under a permit required confined space