Pipeline & Civil Infrastructure
12’ CARBON STEEL LINES
•$15,000,000
• Project Scope, design two 12” carbon steel lines to provide flexibility between two local facilities and main distribution pipe line
• 160 caissons throughout an existing storage tank facility
• Estimated and tracked man hours and costs to complete the project
• Developed an accurate projected schedule including coordinating tie ins with multiple operating unit outages
• Identifying constructability analysis
Featured Performance
PAST PERFORMANCE LEDGER
Mainline Transmission & Gathering:
Installation of 400+ LF of 6” Schedule 40 carbon steel systems including knock-out drum integration.
Turnkey installation of high-pressure gathering lines utilizing Zap-lok and Flexsteel technology for rapid deployment.
Execution of 100 LF of 2” Schedule 80 socket-weld condensate lines for facility tie-ins.
Civil & Right-of-Way (ROW) Management:
Large-Scale Utility Clearing: Comprehensive brush clearing and vegetation management for multi-mile transmission corridors.
Advanced Earthwork: Precision ditching and trenching for multi-line bundles in diverse soil conditions.
Road & River Crossings: Managing horizontal boring and "Live Line" crossing protocols with 100% safety compliance.
Testing & Integrity:
Hydrostatic Testing: High-pressure validation of new and existing mainline assets to ensure jurisdictional compliance.
Anomaly Excavation: Strategic "Integrity Digs" and structural reinforcements for buried pipeline assets.
Specialty Project
CHEMICAL PLANT
• $50,000
• Replace Existing Tank Bottom with New Material
• Open Top Tank inside a manufacturing facility
• Cut off and reinstall existing anchor chairs
• Replacement was under a permit required confined space