
Capital Improvement
CAPITAL IMPROVEMENT PROJECTS
SCE
$1,750,000
Replaced 7 Main Steam Valves in two weeks working two shifts
Valve body material: ASTM A217
Piping Material:
ASTM P91, Inlet 16”Schedule 160, Outlet 12”Schedule 160
100% Weld Acceptance
GE POWER & WATER
$2,4000,000
Replaced hot gas path stainless steel piping in 4 units
90 welds, 316 stainless steel sizes 8” to 4”
Install stainless steel tubing for instrumentation 1,00 linear feet
Passivation of stainless-steel field welded components
100% Weld Acceptance
Submitted R1 form and quality control package following completion of the project
BP WATSON COGEN
• $455,000
• Replacement in kind 6” Steam Return Line
• 400 LF, 6” schedule 40 carbon steel system
• 4 knock out drums
• 100 LF of 2” schedule 80 socket weld condensate line
SCATTERGOOD POWER GENERATING FACILITY
• $75,000
• Replaced 14 - 2” Schedule 80 Carbon Steel Steam Valves
• Replaced 2 – 2” Schedule 120 P91 Steam Valves
SCE
$1,5000,000
Install 16” Stainless Steel Reclaimed Water Line
Install 24” Carbon steel Boiler Feed Water Line
Boiler Repair and Maintenance since 2008
Install Main Boiler Feed Water Valves, P91 Material, 2” thick Piping Wall
NALCO
$145,000
Replaced Vertical Legs of 15 Pressure Vessels in place
Replaced Bottom Heads of 15 Pressure Vessel in Place
Designed and built temporary structures to hold pressure vessels in place during leg and bottom head replacement
100% Weld Acceptance
SAN GABRIEL VALLEY WATER
$3,200,000
Retrofitted an existing warehouse into a UV Reactor Treatment Facility
Ultraviolet Light Advanced Oxidation Treatment System Installation
Constructed concrete pads and imbedded anchors to support new system
Added structural bracing and reroofed existing building
Set 6 exchangers and interconnecting 20” piping
Set a 20’X40 hydrogen peroxide tank
Installed 2 sets of process pumps
Placed and welded 477 linear feet of 18” steel cement-lined pipe
Hot tapped into existing city waterline
CLOROX
$50,000
Replace Existing Tank Bottom with New Material
Open Top Tank inside a manufacturing facility
Cut off and reinstall existing anchor chairs
Replacement was under a permit required confined space